New Page 1
 

Concrete Piles
 

 
  INTRODUCTION:
Prestressed Concrete Circular Spun Piles are an International phenomenon and are in use all over the World particularly in Japan and Germany for quite sometime. In recent times spun piles have been taken to use extensively in neighbouring countries like Malaysia, Indonesia, Taiwan and Korea.

TECHNOLOGY:
HBL in the process of product diversification from spun poles, have developed a design for spun piles, manufactured a prototype and got the same tested at Indian Institute of Technology, Madras. The test results are as under:
 
Indian Test Japanese Test % increase
Axial Load Bending Moment
242.0 15.3
Axial Load Bending Moment
172.0 6.6
Axial Load Bending Moment
40.1 131.8

From the above test results, it would be apparent that the product is comparable to International Standards. HBL has the technical know-how and machinery for commercial manufacture of piles.

SPLICE JOINTING:
The joint welding procedure for piles longer than 12 metres is a well-known method adopted in a number of countries. The method involves circumferentially welding together the plates (mild steel, annular discs) firmly embedded in concrete at ends of piles. The welded joint has strength equal to that of the concrete portion of the pile. The joint details are given in sketch below.

UNIFORM STRENGTH AND HIGH PRODUCT RELIABILITY:
HBL PC-PILES are manufactured by centrifugal compaction process which gives uniform and assured strength with high reliability. Concrete of grade M-50 is used in the manufacture of piles.

DURABILITY:
Even if there be a tensile load on the pile during transportation, handling or pile driving work, the prestress prevents occurrence of any cracking in the pile. However, if crack appears due to sudden excessive tensile load of temporary nature such cracks will disappear as soon as the load is removed. The possibility of corrosion of the prestressing steel wires is, therefore, remote and life of spun piles is longer.

COST EFFECTIVE:
In the conventional piles, driven or cast-in-situ, a minimum of 2% reinforcing steel has to be provided as per relevant code whereas the prestressing steel in spun piles is 0.50% to 0.60% leading to a saving in cost of pile.

PILE DRIVING:
Spun piles do not require any special driving equipment. The conventional hammers can be used for pile driving.

ADVANTAGES OF HBL SPUN PILES:

  • Manufactured in longer length up to 12 m.
  • Low unit weight, hence lower cost.
  • High strength concrete of 500 kg/sqcm is used.
  • Spinning results in denser concrete, reduces water cement ratio and hence increases concrete strength further.
  • High flexural strength.
  • Absence of torsional cracking.
  • High resistance to corrosion especially from sea water.
  • Consistent quality under factory conditions.
  • High rate of production ensures early completion of projects.
  • Eliminate casting yard at site – a distinct advantage in urban re-development projects.
  • High early strength enables the pile to be driven 10 days after manufacture.
MANUFACTURING PROCESS The process consists of several activities starting from raw materials to testing and despatch.

The source of raw materials for concrete, cement, natural stone aggregate and sand are identified and materials tested for suitability. Similarly, H.T. wires conforming to stipulations are procured from renowned manufacturer and test reports verified.

H.T. wires are cut to required size of poles with a margin of about 300 mm and button heading done at ends of pretensioning. Cages are formed with M.S. Wires for helical reinforcement.

The cage is placed in the bottom half of the mould and the calculated quantity of concrete is placed. The top half is than bolted and prestressing of H.T. wires done by a hydraulic jacking system. The mould is then placed on spinning machine and spun at predetermined speeds and duration.

The spun mould is placed in a sump for steam curing for six hours at 65 degrees Celsius. The demoulded piles are placed in a water sump for normal curing. The top & bottom open ends are sealed with cement mortar.

The poles are inspected, marked and stacked for testing and despatch.

Stagewise inspections and testing of material, concrete and poles are carried out. Bent test is carried out on random selected poles as per provisions of IS codes.

TECHNICAL SPECIFICATION FOR PRESTRESSED SPUN CONCRETE PILES

1. SCOPE:
This specification covers design, manufacture, testing and supply of prestressed concrete circular SPUN piles.

2. MATERIALS:
2.1 High strength ordinary Portland cement conforming to IS:8112 or ordinary Portland cement conforming to IS:269, which shall have the following additional requirements, shall be used.

a) Initial Setting Time : Not less than 90 minutes.
b) Final Setting Time : Not more than 600 minutes.

2.2 As far as possible cement shall be obtained from the same source to minimize variation in quality.

3. AGGREGATES:
3.1 Coarse and fine aggregates used for manufacture of piles shall be from natural source conforming to IS: 383-1970. The nominal maximum size of aggregates shall in      no case exceed 20mm provided further that the size of aggregates shall be atleast 5mm less than the spacing between the prestressing wires.
3.2 Each size of aggregates shall be stocked in different storage bins or stock piles and shall be mixed only after the quantity required for each size has been      separately weighed.
3.3 Water:
     Water shall be free from chlorides, sulphates, other salts and organic matter. Portable water shall generally be suitable.
3.4 Admixtures:
    Admixtures, if used, shall not contain calcium chloride or other chlorides and salts which are likely to promote corrosion of pre-stressing steel. Use of any     admixture shall be got approved by the Engineer-in-charge.
3.5 Reinforcement:
3.5.1 Reinforcement bars and high tensile prestressing wires used for the manufacture or prestressed concrete piles shall conform to the following Indian Standards.

a) IS: 1785 (Part-I) – Specification for plain hard drawn steel wire for prestressed concrete: Part-I cold drawn stress relieved wire (second revision).
b) IS:1785 (Part-II) – Specification for plain hard drawn steel wire for prestressed concrete: Part-II as drawn wire (first reivision).
c) IS: 2090:1983 – Specification for high tensile steel bars used in prestressed concrete (first revision).
d) IS: 6003:1983 – Specification for indented wire prestressed concrete (first revision).
e) IS: 6006:1983 – Specification for uncoated stress relieved strand for prestressed concrete (first revision).
3.5.2 The surface of all high tensile and reinforcement bars shall be free from loose scale, oil, grease, clay or other material that may have detrimental effect on the         bond between the bars and the concrete.

4. CONCRETE:
    The concrete mix shall be designed to meet the requirement stipulated in IS:456 (code of practice for plain and reinforced concrete) or IS:1343 (code of practice     for prestressed concrete).

a) Minimum works test cube strength at 28 days shall not be less than 50N/Sqmm. In occasional cases where the minimum works test cube crushing strength falls below    50N/Sqmm but not below 47N/Sqmm may be accepted subject to increased frequency of tests.
b) The concrete strength at transfer shall be atleast half the 28 days strength adopted in the design or strength adopted for transfer or prestress.

5. MANUFACTURE OF PILES:
5.1 Moulds:
     Moulds shall be of steel and of rigid construction to prevent distortion and so arranged as to provide smooth surfaces. The moulds shall not allow any leakage of     cement slurry during spinning. The holes in the end plates for prestressing wires shall be accurately drilled to ensure inter-changeability. The end plates shall be     designed to withstand the forces arising out of the change in direction of prestressing wires during tensioning.

5.2 Tensioning of Wires:
5.2.1 The H.T. wires shall be placed axially at regular spacing along the circumference. The spacing shall be as per IS:13158.
5.2.2 Helical steel shall be 3.2mm dia M.S. wires and the pitch shall be 150mm.
5.2.3 The clear cover shall be 20mm.
5.2.4 Pre-tensioning shall be by automatic machines. Force shall be applied on the entire group of H.T. wires to ensure all wires are equally stressed.
5.2.5 The anchoring of the prestressed wires shall be such that during manufacture and until the wires are released, no slipping occurs. The force at the time of initial        stretching, in addition to imparting of designed prestress, shall also be sufficient to overcome the friction on account of any change in the inclination of wires        and slippage that might occur during the anchoring process which shall be suitable
5.2.6 The tensioning of prestressing steel shall be carried out in a manner that will induce a smooth and even rate of increase of stress in the wires.
5.2.7 The force induced in the prestressing wires shall be determined by means of pressure gauge attached to the tensioning equipment and cross checked by an        elongation scale determined in advance. The accuracy of the devices for measuring of the tensioning force shall be within plus or minus 5%.

5.3 Mixing and consolidation of Concrete:
5.3.1 Provision shall be made to measure the quantities of cement, fine and coarse aggregates by weight only. The accuracy of the measuring equipment shall be plus        or minus 3%. All the measuring equipment shall be maintained in clean, serviceable condition and accuracy checked at regular intervals. Modern high speed        mixers, preferably pan type, shall be used.
5.3.2 The freshly cast piles shall be protected during the first stage of hardening from harmful effects of sunshine, dry winds, cold rains.

5.4 Curing:
5.4.1 The curing shall be done with saturated steam at 65 degree celsius to ensure that concrete strength for release of prestress as adopted in design is reached in        6/8 hours. Thereafter the H.T. wires shall be cut, poles demoulded and cured in water in sumps or by sprinklers for atleast 7 days.
5.4.2 During manufacture, periodical tests on concrete cubes shall be carried out till the concrete achieves the required strength at transfer. Thereafter, the test on        concrete shall be carried out a s detailed in IS:13148/IS:456. The Manufacturer shall, if so required by the purchaser, furnish results of compressive test        conducted in accordance with IS:456 on concrete cubes made from the concrete used for the piles. If the purchaser so desires, the manufacturer shall supply        cubes for test purposes and such cubes shall be tested in accordance with IS:456.

5.5. Detensioning of Wires:
5.5.1 The anchoring system shall provide a device for gradual detensioning of the wires. No back pulling of the wires shall be permitted in the gradual detensioning         device for the purpose of release of any wedge or other parts of the detensioning device. Flame cutting of the wires before release of the full tension shall be         strictly prohibited.
5.5.2 The transfer of prestress shall not be effected until the concrete in the piles has attained the specified strength as established of cube tests.

6. TESTS:
6.1 During manufacture, tests on concrete shall be carried out.

7. MARKING:
    The piles shall be clearly and indelibly marked with the following particulars either during or after manufacture but before testing at a position so as to easily read     after erection in position:
    a) Month and year of manufacture.
    b) Transverse strength of pile in Kg.
    c) Serial number of the pile.
    d) Position of centre of gravity of the pile with the word C.G.

Brochure for Details.

 

 
 

All © Rights Reserved to HBL Power Systems Limited. Designed by HBL Corporate Communications.